As of today we have 9 of 35 moorings completed and expect to be done with this phase by August 31, 2012. This accounts for Phase 1 of 3 phases. Based on this it is necessary for all boats currently moored or anchored in the Sarasota bay front to move to allow for proper use of the new moorings. Attached is a notice that includes a map of the mooring field limits.
We are excited that completion of Phase 1 has progressed so effectively and look forward to starting phase 2 in the near future.
Should you have any questions related to this project do not hesitate to contact me and please share this information with anyone else you feel may benefit from it. If you wish to be removed from this distribution list please forward this email back to me with a note to remove you from the list.
Sincerely,
Tony
Anthony D. Russo, P.E.
City of Sarasota Public Works