Update on Vuecrest Sewer Project

CB
CHRIS BODIFORD
Tue, Apr 7, 2020 11:21 PM

Dear Neighbors - I am attaching a letter that the City has prepared to provide Vuecrest residents with an update on the sewer lining work being done in the neighborhood.  As you know the stay-at-home order issued back in March has put a temporary stop to the construction work in Vuecrest sewer project.  The governor then issued a clarification that has allowed utility construction work, such as the Vuecrest project, to continue as long as safety protocols are followed.  This will allow Insta-Pipe to resume work on Monday, April 13th.

Best, Chris

Dear Neighbors - I am attaching a letter that the City has prepared to provide Vuecrest residents with an update on the sewer lining work being done in the neighborhood. As you know the stay-at-home order issued back in March has put a temporary stop to the construction work in Vuecrest sewer project. The governor then issued a clarification that has allowed utility construction work, such as the Vuecrest project, to continue as long as safety protocols are followed. This will allow Insta-Pipe to resume work on Monday, April 13th. Best, Chris
EW
Ellen Wang
Wed, Apr 8, 2020 12:01 AM

That will be nice! There is a big hole about 5 or 6 feet deep in my back
yard since January. I really want the construction to be done as soon as
possible. I also worried about my flowers bed might not come back this
summer. :(

Ellen Wang
9446 Vineyard Crest

On Tue, Apr 7, 2020 at 4:27 PM CHRIS BODIFORD chrisbodiford@msn.com wrote:

Dear Neighbors - I am attaching a letter that the City has prepared to
provide Vuecrest residents with an update on the sewer lining work being
done in the neighborhood.  As you know the stay-at-home order issued back
in March has put a temporary stop to the construction work in Vuecrest
sewer project.  The governor then issued a clarification that has allowed
utility construction work, such as the Vuecrest project, to continue as
long as safety protocols are followed.  This will allow Insta-Pipe to
resume work on Monday, April 13th.

Best, Chris


Everyone mailing list
Everyone@lists.vuecrest.net
http://lists.vuecrest.net/mailman/listinfo/everyone_lists.vuecrest.net

--

Ellen Wang

*305 108th Avenue NE, Suite 200. *

Bellevue, WA 98004

O: 425.637.7777 • M: 425.985.3888

That will be nice! There is a big hole about 5 or 6 feet deep in my back yard since January. I really want the construction to be done as soon as possible. I also worried about my flowers bed might not come back this summer. :( Ellen Wang 9446 Vineyard Crest On Tue, Apr 7, 2020 at 4:27 PM CHRIS BODIFORD <chrisbodiford@msn.com> wrote: > Dear Neighbors - I am attaching a letter that the City has prepared to > provide Vuecrest residents with an update on the sewer lining work being > done in the neighborhood. As you know the stay-at-home order issued back > in March has put a temporary stop to the construction work in Vuecrest > sewer project. The governor then issued a clarification that has allowed > utility construction work, such as the Vuecrest project, to continue as > long as safety protocols are followed. This will allow Insta-Pipe to > resume work on Monday, April 13th. > > > > Best, Chris > > > _______________________________________________ > Everyone mailing list > Everyone@lists.vuecrest.net > http://lists.vuecrest.net/mailman/listinfo/everyone_lists.vuecrest.net > -- *Ellen Wang* *305 108th Avenue NE, Suite 200. * *Bellevue, WA 98004* *O: 425.637.7777 • M: 425.985.3888*