I agree with John on this one - put in another meter socket
downstream if you really want to experiment, and be sure to have a
main disconnect besides the utility's meter.
If you are changing the service entrance, you will likely have issues
with the local permits for it, and with the utility company - they
don't like to see anything unusual or confusing.
A couple of years ago I put in a new service at our vacation house,
that had an ancient mish-mosh of crap that was ready to catch on
fire, stuffed into too small a panel, and with no main disconnect
except by pulling the utility meter outside. I collected a nice new
meter box/load center and other needed parts, assuming I could just
have PGE pull the meter outside, replace the old load center with the
new, and have my own meter and disconnect inside. When I applied for
the permit from the county, this caused nothing but grief and
confusion - they didn't understand, and neither did PGE, why anyone
would want a second meter. They get suspicious I think, because they
don't want multiple residences set up on single-residence zoning, so
another meter is a red flag, even though I explained many times that
it was just in series, for monitoring and alternative energy
experiments such as grid-tie stuff to come later. Furthermore, I had
to make it meet all current codes, which meant I needed to have a
separate disconnect on the outside, and updated grounding.
Ultimately, I ended up replacing the whole works with my new
meter/load center on the outside, with PGE's meter installed, and
another new meterless load center on the inside. It all worked out
OK, but it became a week-long project involving a big hole in the
wall and reframing, instead of a one day quick-changeout as I had planned.
I can now change it and add meters and CTs and whatever, downstream,
but I kind of lost interest after going through all that. The novelty
wears off quickly when you have to first get all the basic stuff
properly working.
Also, whatever you add should be done in ways that are safe common
sense-wise, and meet electrical codes. A mistake in fooling with a
typical 200A 240V main may cause much more than a spark and a pop.
Ed
On 04/30/2014 02:01 PM, ed breya wrote:
When I applied for the permit from the
county, this caused nothing but grief and confusion - they didn't
understand, and neither did PGE, why anyone would want a second meter.
At my last house when the place was rewired after a fire, I anticipated
this problem. I had the electrical contractor move the meter base about
4 ft away from the breaker panel and install the service disconnect on
the far side of the meter. That gave me about 5 ft of conduit inside
the house from the wall penetration to the breaker panel - plenty of
room to cut in and add the second meter base after the inspection.
Worked like a champ.
John
--
John DeArmond
Tellico Plains, Occupied TN
http://www.fluxeon.com <-- THE source for induction heaters
http://www.neon-john.com <-- email from here
http://www.johndearmond.com <-- Best damned Blog on the net
PGP key: wwwkeys.pgp.net: BCB68D77